Almost every rehab costs more than the first estimate. The goal is not a perfect budget. The goal is to see the overage early, decide on it deliberately, and know what it does to your profit. This guide covers how to do that.

Budget each job, then track the actual cost

Split the rehab into jobs, such as demolition, kitchen, bathrooms, flooring, and paint. Give each job a budget, which is what you planned to spend. As work happens, record the actual, which is what you really paid. The gap is your early warning.

Also track each job's status: not started, in progress, or complete. A job at 90% of budget and half done is a problem. A job at 50% of budget and half done is on track.

Handle changes with change orders

A change order is a formal request to change a job's scope or cost. A rotted subfloor, a code fix, or an upgrade you want are all common causes. Write it down, price it, and approve or reject it before the work is done.

When you approve one, two things must rise: that job's budget, and the deal's rehab estimate. If you raise only the job budget, your project looks fine while your profit quietly shrinks.

Pay for completed work

A draw is a payment request for finished work on one job. Before you approve one, check three things: you have reviewed completion photos, the work is marked complete, and any inspection is done. Then pay. This keeps you from paying for work that is not finished.

Inspect before you pay

Look at the work yourself, or have someone qualified look at it. An inspection can find problems while the contractor is still on site and still motivated to fix them. A punch list, the final list of small fixes, is easier to close when issues are caught as you go.

Read original versus current profit

This is where budget changes show up in real money. Here is an example with round numbers. You buy at $149,400, with an ARV of $250,000 and a $40,000 rehab. Default holding, financing, and selling costs apply.

ItemOriginalCurrent
Rehab$40,000$43,200
Profit$38,100$34,900
ROI18.0%16.2%
Margin15.2%14.0%

A single $3,200 change order cut profit by $3,200. That is still above a $25,000 minimum, but ROI and margin now fall below the 18% and 15% defaults. Small overages can move a deal from passing to failing, which is why you watch them.

The honest limit: holding costs

A late project costs more than its repair bills. You pay interest, taxes, insurance, and utilities for each extra month. In the app, holding costs do not grow on their own. If the job runs long, you will see it as a later completion date, but your profit does not change unless you edit the holding costs yourself.

So when the schedule slips, update the number. For example, adding $1,500 of holding costs to the example above would take current profit from $34,900 to $33,400.

Common mistakes

  • Approving extras verbally and never recording them.
  • Raising a job budget without updating the deal's rehab number.
  • Paying ahead of the work.
  • Ignoring a slipping schedule.
  • Only checking the total, not each job.

How GenesisOS does it

In Rehab Projects, you start a project from a deal. The app snapshots the original projected profit. A project moves through Planning, Bidding, Contractor Selected, Ready to Start, In Progress, Inspection / Punch List, Completed, and Closed. Each job has a budget and an actual cost. Job photos, job inspections, and callbacks are stored with the job.

Draws are tied to one job. Paying a draw records that job's actual cost. The Rehab Quality setting is Off, Notice, or Block. A failed latest inspection or an open callback can warn you, or block you from approving a draw. Approving a change order raises the job budget and the deal's rehab estimate, so profit updates automatically.

The Deal Health Monitor compares original and current projected profit and explains the change by cause: rehab overage, ARV adjustment, holding, financing, selling costs, and acquisition costs. Completion-date drift is reported separately.

Key takeaways

  • Give every job a budget and record the actual cost.
  • Approve changes in writing, and raise both the job budget and the deal's rehab number.
  • Pay draws only for finished, checked work.
  • Compare original and current profit, not just the repair total.
  • Holding costs do not accrue by themselves, so update them when the schedule slips.